Sindh Public Procurement Rules 2010 (SPPRA) — summary

Applies to: Sindh government departments, attached departments, autonomous bodies and local councils in Sindh.

Sindh procurement follows the Sindh Public Procurement Act, 2009 and the Sindh Public Procurement Rules, 2010, regulated by the Sindh Public Procurement Regulatory Authority (SPPRA) in Karachi.

Advertising

  • Above Rs 1 million and up to Rs 2 million: on the SPPRA website (print optional).
  • Above Rs 2 million: SPPRA website and newspapers — at least three widely read dailies in English, Urdu and Sindhi.
  • International bids are also advertised in English internationally.

Time to bid

At least 15 calendar days for national competitive bidding and 30 calendar days for international competitive bidding. International bidding is the default from US$10 million.

Other methods

Method When
Petty purchase Below Rs 100,000
Request for quotations (at least three) Below Rs 1 million
Direct contracting Only in listed cases (standardisation, proprietary items, emergencies with recorded reasons)
Repeat orders Up to 15% of the original contract; goods within the same financial year

Securities and validity

  • Bid security: up to 5% of estimated value; released to unsuccessful bidders within 7 days of contract signing or validity expiry.
  • Bid validity: up to 90 days (national) or 120 days (international).
  • Performance security: up to 10% of contract price.

Evaluation report

The evaluation report is posted on the SPPRA and agency websites and sent to bidders at least 3 working days before award.

Complaints and review

  • The agency's Complaint Redressal Committee decides within 7 days.
  • Appeal to SPPRA's Review Committee within 10 days (bid security must still be deposited). The Review Committee decides within 10 working days; its decision is final.
  • No contract may be signed until the appeal period ends or the Review Committee decides.