Every government tender in Pakistan follows the procurement rules of whoever is buying. A federal ministry or federal company follows the federal PPRA rules. A provincial department follows its own province's rules. Azad Jammu & Kashmir and Gilgit-Baltistan have their own procurement laws too. The rules decide how long you get to bid, how much bid security can be asked, where the tender must be advertised and how you can complain.

On every tender page on PakOpportunities we show which rules apply. Use the tabs above for each set of rules.

Quick comparison

Federal Punjab Sindh Khyber Pakhtunkhwa Balochistan
Main rules Public Procurement Rules 2026 Punjab Procurement Rules 2014 Sindh Public Procurement Rules 2010 KP Public Procurement of Goods, Works and Services Rules 2014 Balochistan Public Procurement Rules 2014
Regulator PPRA (Islamabad) PPRA Punjab SPPRA KPPRA BPPRA
Minimum time to bid (national / international) 10 / 20 days 15 / 30 days 15 / 30 days 15 / 30 days 15 / 45 days
Bid security cap 5% (2% above Rs 250 million) 5% 5% 2% (goods up to 5% if complex) 2% (up to 5% if complex)
Online / newspaper advertising EPADS above Rs 200,000; newspapers above Rs 5 million PPRA website above Rs 500,000; newspapers above Rs 5 million SPPRA website above Rs 1 million; newspapers above Rs 2 million Websites from Rs 500,000; newspapers above Rs 5 million BPPRA website above Rs 100,000; newspapers above Rs 1 million*
Evaluation report before award Published on EPADS before award At least 10 days At least 3 working days At least 10 days At least 10 days
Electronic bidding EPADS mandatory e-procurement for notified agencies; EPADS widely used EPADS directed for all departments EPADS widely used EPPS (Electronic Public Procurement System)

Azad Jammu & Kashmir (AJ&K Public Procurement Rules 2017, AJK PPRA) and Gilgit-Baltistan (GB Public Procurement Act 2021 and GBPPRA Rules 2022, GB PPRA) have their own tabs.

*Balochistan figures are from the rules as notified in December 2014; some limits have been amended since. Always confirm with the regulator.

Which rules apply where

Where the buyer is Rules
Federal ministry, division, federal company or authority (anywhere in Pakistan, including Islamabad) Federal PPRA rules
Punjab government department or body Punjab rules
Sindh government department or body Sindh rules
KP government, including Swat, Dir, Chitral, Buner, Shangla, Malakand and the other former PATA districts, and the merged former FATA districts (Bajaur, Mohmand, Khyber, Kurram, Orakzai, North and South Waziristan) KP rules
Balochistan government department or body Balochistan rules
AJK government (Muzaffarabad, Mirpur, Kotli, Bagh, Rawalakot, Neelum and others) AJK rules
Gilgit-Baltistan government (Gilgit, Skardu, Hunza and others) GB rules

The city does not decide the rules — the buyer does. A federal tender in Swat or Skardu follows the federal rules.

What every bidder should check

  • The deadline counts from the publication date, not from the date you saw the tender. Bid early.
  • Bid security is usually a pay order, bank guarantee or call deposit, sometimes replaced by a bid-securing declaration. Check the exact form in the bidding documents.
  • Read the evaluation report when it is published. Complaint windows are short — often 5 to 10 days.
  • Corrigenda change tenders. PakOpportunities tracks changes to closing dates and shows them on each tender.

This guide is a summary written by PakOpportunities to help bidders. It is not legal advice and does not replace the official rules, which are linked on each page.