Punjab Procurement Rules 2014 (PPRA Punjab) — summary

یہ رہنما فی الحال صرف انگریزی میں دستیاب ہے۔

Applies to: Punjab government departments, attached offices, autonomous bodies, local governments and other procuring agencies of the Punjab.

Punjab procurement follows the Punjab Procurement Regulatory Authority Act, 2009 and the Punjab Procurement Rules, 2014, regulated by PPRA Punjab in Lahore. This summary follows the rules as amended up to 24 September 2025.

Advertising

  • Procurement above Rs 500,000 must be advertised on the PPRA Punjab website.
  • Above Rs 5 million it must also go on the agency's own website (if it has one) and in at least two national daily newspapers, one English and one Urdu.

Time to bid

At least 15 days for national competitive bidding and 30 days for international competitive bidding, counted from publication on the PPRA Punjab website.

Methods and limits

Method When
Petty purchase (no bids or quotations) Up to Rs 200,000
Quotations (at least three) Above Rs 200,000 and up to Rs 500,000
Competitive bidding Above Rs 500,000 — single-stage one-envelope is the main procedure; single-stage two-envelope and two-stage procedures are also allowed
Direct contract Only in listed cases; repeat orders up to 15% of the original procurement
Negotiated tender Only in listed cases (some need Provincial Cabinet approval)

Securities and validity

  • Bid security: up to 5% of the estimated price.
  • Bid validity can be extended in exceptional cases, by no more than the original validity or 180 days, whichever is more, with approval from the next higher authority.
  • Performance guarantee: up to 10% of the contract amount.

Evaluation report

The evaluation result must be announced at least 10 days before the contract is awarded.

Complaints

  • Lodge a written complaint with the agency's Grievance Redressal Committee within 5 days of the technical evaluation report and 10 days after the final evaluation report.
  • The committee decides within 15 days.
  • You can then make a representation to the Managing Director of PPRA Punjab within 7 days of the committee's decision.

E-procurement and blacklisting

Agencies notified by PPRA Punjab must procure electronically (rule 3A); many Punjab tenders now run on EPADS and the Punjab e-Procurement System. Bidders can be debarred for a specified period under rule 21; a representation against debarment goes to the Managing Director within 30 days.